On Tuesday, by mid-morning, they had cut back the rafters across the 'front door side' (dining room, kitchen, front hallway and office).


The living room outer wall and roof is being removed up to the steel beam.


By mid-afternoon, a fair amount of the living room roof and wall was gone.


The blur of activity is all in preparation to install the SIPs (Structural Insulated Panels) roof panels, arriving here.  The installation is to happen on Wednesday before it starts raining again, early Thursday...


They finished quite late, so at the end of the day we had a carport full of SIPs...


An open air living room...

And a new sign!